Stoke Mains Renewal

Staffordshire 

We’re investing in Stoke's future

Severn Trent is investing £25million in Stoke-on-Trent as part of an ambitious multi-million pound scheme to replace ageing water pipes and provide the city with a more reliable water supply.

Work is set to begin on the delivery of a major project of upgrades to the water network in Stoke, modernising infrastructure and ensuring its resilience for the future.

Crews are set to start working to install approximately over 40 kilometres of new pipe in Stoke-on-Trent from April 1st, 2025, with the programme of works going ahead in the Hanley, Burslem and Sneyd Green areas.

The installation will be phased across the area and is planned to start with Milton Road, Berwick Road, Birches Head Road and Fairfax Street. The whole of the project is expected to be completed by April 2027.

Ahead of the work beginning, the team will be looking to meet with the local community and talk about the project.

 

Severn Trent Water's
Free Shuttle Bus

Conecting Stanton's of Stoke, First Buses and D&D bus services across Sneyd Green and Hanley while our works are completed on Hanley Road. 

Monday to Saturday - Every 30 minutes

Sunday - Every 60 minutes, 6:30am until 7:30pm 

 

*Subject to change to suit and fulfil customers requests and needs. 

 If you have any queries in relation to bus routes, please contact Stoke-on-Trent Council on 01782 234234, Stantons of Stoke on 01782 827282 or visit the Travel & Information shop at Hanley bus station.

 