Wollerton, Market Drayton, Telford
We're carrying out some water pipe renewal works from 29 October 2018 in Wollerton area of Market Drayton, starting by Wollerton Hall Gardens, working in sections towards Mill Road, then onto the main road in the direction of Lostford. We expect to complete the work by March 2019.
What's our Progress?
1 Jobs In Progress
1 Jobs Complete
Between 29 Oct 2018 to 08 Mar 2019
Why are we doing this?
Preventing sewer flooding
We're upgrading someof the existing water pipes in the Wollerton area of Market Drayton with new ones to help prevent the risk of bursts and flooding.
Five months in the works
We plan to start working at on 29 October 2018, we expect our works to take around five months to complete.
Communities first
We'll be be at Wollerton URC Church School Room, Wood Lane, Wollerton, TF9 3NY on 11 October 2018 from
3:30pm – 7pm, if you'd like to drop in and see us and we can share our plans with you.