In My Area

Walton Cardiff

We plan to replace 1.6 kilometres of sewage pumping mains serving the Walton Cardiff sewage pumping station. This is because due to their age the material has become brittle and has suffered a series of bursts, resulting in the risk of pollution of the local rivers.

Our progress so far

We’re still committed to reducing the risk of bursts from the existing sewage pumping mains by constructing a new replacement pumping main. The next stage of the work will involve the final connections, to complete this work we need to isolate the pumping station in the village and remove the waste from site via tankers. During this work, you will notice an increase in general activities covering a 24 hour period. 

Please be assured that we along with our contract partner, Mott MacDonald Bentley (MMB), will do our best to keep any noise and on-site activities to a minimum during the work and we are sorry for any inconvenience that we may cause. The site team will continue their face to face communications with those that are directly affected by the works, as they progress.

The tanker activity will start on site from Tuesday 5 October 2021 and is due to be completed by mid day, Wednesday 6 October 2021.

Our team are continuing to work within the social distancing guidelines set out by the government, keeping two metres apart where possible. We’ve ensured that our processes have been updated so that our work can be carried out with everyone’s safety as a priority, during these difficult times.

COMPLETE

Our Progress

Start date

29 June 2021

Upcoming work

Work in Progress

Work completed

Work is now complete on Queens Road

Estimated completion date

20 July 2021

IN PROGRESS

Road Closure

To allow us to carry out this work quickly and safely, our team will be working under a road closure.

Roads affected:

Wenlock Road

Our Progress

Start date

7 June 2021

Upcoming work

Work in Progress

Work is progressing well on Wenlock Road and our team expect to be finished and off the road by early September.

Work completed

Estimated completion date

Early September

Our Progress

Start date

5 May 2021

Upcoming work

Work in Progress

Work completed

Work is now complete on this section.

Estimated completion date

4 June 2021

Taking care of one of life's essentials


Let us know how we're doing

Please get in touch if you have any feedback about our works.


Meet the team

Ian Woodward

Severn Trent Water Project Manager

07789 903278