We are returning to Worcester City Centre, to begin phase two of our £1.25m project to replace ageing water pipes. We completed the first phase of the pipe replacement project on The Shambles, and will now start work again on Pump Street to improve the water network for those living and working in the area

Our progress so far

COMPLETE - 23 MAR 2020

Complete - 100%

Start date

25 February 2020

Work completed

New Street
Work is now complete in New Street and we are currently working on the junction of Pump Street and Charles Street.

Work in Progress

Upcoming work

Estimated completion date

23 March 2020

IN PROGRESS - 22 APR 2020

Traffic cone icon

Road closure

We plan to start our work in Pump Street from 3 February 2020 to renew the remaining sections of water main, and to allow us to complete this work quickly and safely we will have a road closure in place.

Roads effected:

Charles Street

Progress - 0%

Start date

23 March 2020

Work completed

Work in Progress

Charles Street
We are currently working at the junction of Charles Street and Pump Street. Charles Street will be closed until the end of June.

Upcoming work

Estimated completion date

22 April 2020

IN PROGRESS - 22 MAY 2020

Traffic cone icon

Road closure

We plan to start our work in Pump Street from 3 February 2020 to renew the remaining sections of water main, and to allow us to complete this work quickly and safely we will have a road closure in place.

Roads effected:

Pump Street

Progress - 0%

Start date

23 March 2020

Work completed

Work in Progress

Upcoming work

Pump Street - phase two
We plan to start our work in Pump Street from 3 February 2020 to renew the remaining sections of water main, and to allow us to complete this work quickly and safely we will have a road closure in place.

Estimated completion date

22 May 2020

IN PROGRESS - 29 JUN 2020

Progress - 0%

Start date

1 June 2020

Work completed

Work in Progress

Upcoming work

We plan to start work in St Swithins street on 1 June and the work should take four weeks to complete. St Swithins Street will remain open with certain vehicle restrictions.

Estimated completion date

29 June 2020

IN PROGRESS - 22 MAY 2020

Traffic cone icon

Road closure

The road will be closed during our works, so that we can keep our workforce and you safe.

Roads effected:

Friar Street

Progress - 0%

Start date

23 March 2020

Work completed

Work in Progress

Upcoming work

Friar Street
Our work will begin 23 March 2020 to 22 May 2020.

Estimated completion date

22 May 2020

COMPLETE - 24 FEB 2020

Complete - 100%

Start date

3 February 2020

Work completed

Pump Street – phase one
We have now completed our works on phase one Pump Street.

Work in Progress

Upcoming work

Estimated completion date

24 February 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.