In My Area

Teversal Village

We’re installing a brand new public sewerage system in Teversal Village. By connecting properties to a public sewer we can protect the environment, public health and give peace of mind to the residents of these communities.

Our progress so far

Between 2015 and 2020 Severn Trent has invested in providing new sewerage systems to rural communities where existing private drainage is causing harm to the environment or a risk to public health. By connecting these properties to a public sewer we can protect the environment, public health and give peace of mind to the residents of these communities. 

IN PROGRESS

Progress - 99%

Start date

23 November 2020

Upcoming work

Work in Progress

Work completed

The work on Buttery Lane is complete, the team will return on 22 February 2021 to complete a vacuum main along the road.

Estimated completion date

12 March 2021

IN PROGRESS

Road closure

To allow us to complete this work quickly and safely we will have road closures in place between 8am and 4pm.

Roads affected:

Manor Close

Progress - 0%

Start date

25 January 2021

Upcoming work

Work in Progress

Whilst our team are working in Manor Close, the road will be closed each day from 8am to 4pm.

Work completed

Estimated completion date

19 February 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely we will have road closures in place between 8am and 4pm.

Roads affected:

Grange Close

Progress - 0%

Start date

22 February 2021

Upcoming work

Whilst our team are working in Grange Close, the road will be closed each day from 8am to 4pm.

Work in Progress

Work completed

Estimated completion date

12 March 2021

Two-way traffic lights

To allow us to complete this work quickly and safely we will have a two-way traffic lights in place.

Roads affected:

Pleasley Road

Progress - 0%

Start date

15 March 2021

Upcoming work

Whilst our team are working in Pleasley Road, there  will be a two-way traffic light in place.

Work in Progress

Work completed

Estimated completion date

9 April 2021

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Helen Purdy

Severn Trent Community Communications Officer

07703 718436