Swinford, Lutterworth

We're carrying out water pipe improvements across Leicestershire to secure water supplies for the future.

Our progress so far

Complete - 100%

Start date

2 November 2020

Upcoming work

Work in Progress

Work completed

Work is now complete in Rugby Road but the team will return on 22 February 2021 to finish work near the entrance to Simons Close.

Estimated completion date

18 December 2020

IN PROGRESS

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place

Roads affected:

Kilworth Road

Progress - 0%

Start date

4 January 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

12 February 2021

UPCOMING

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

High Street

Progress - 0%

Start date

8 February 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

5 March 2021

UPCOMING

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Rugby Road

Progress - 0%

Start date

22 February 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

12 March 2021

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Timothy Ip

Severn Trent Communications Officer

07789 903918