Stroud Resilience Project - Whaddon to Minchinhampton Common

70%

Final phase

27 Dec 2019

Estimated completion date
Upcoming work

Work in progress

Work in progress

We have laid about 4.5km of water main so far, work is progressing well.

New pipeline

We’re investing 11million to make Stroud’s drinking water supply even more resilient for the future. We'll begin working in mid-late summer 2018 until winter 2019 installing 16km of pipe from Whaddon near Gloucester to Minchinhampton Common near Stroud. Bringing wonderful water to 55,000 customers.

Work completed
Start date

17 Sep 2018

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Archaeological findings

This area produced multiple agricultural features and significant quantities of Iron Age and in particular, Roman pottery.

How are we doing?

If you have any feedback about our works, please click the button below.

Why are we doing this?

Meet the team

Amanda Hales

Amey Customer Liaison Officer

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages