Stroud Resilience Project - Oxlynch Lane

100%

Complete

29 Mar 2019

Estimated completion date
Upcoming work
Work in progress
Work completed
Oxlynch Lane

During week commencing 18 March we plan to install the new water pipeline across Oxlynch Lane, Standish. Again we will implement a day time road closure, between the hours of 9:30hrs and 15:30hrs. We anticipate this crossing approximately three days to complete.

Start date

18 Mar 2019

Road closure

Road closure

So that we can work quickly and safely we're closing the road during our works. Please plan your journey to avoid delays.

  • Roads effected:
  • Oxlynch Lane

There are currently no disruptions

There are currently no disruptions

Archaeological findings

This area produced multiple agricultural features and significant quantities of Iron Age and in particular, Roman pottery.

How are we doing?

If you have any feedback about our works, please click the button below.

Why are we doing this?

Meet the team

Amanda Hales

Amey Customer Liaison Officer

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages