Stroud Resilience Project - Ebley Road

90%

Final phase

27 Mar 2020

Estimated completion date
Upcoming work
Work in progress
Ebley Road

This week we plan to lay the new water pipe between the railway line and Ebley Road and take two - three weeks to complete. Following this final work we begin the reinstatement of the land where we've already worked.

Work completed
Ebley Road

During week commencing 25 November 2019, we will begin to construct the pit adjacent to 22 & 23 Renard Rise and this should take approximately one week to complete. The sound proof panels will be placed on the fencing. We plan to commence the tunnelling under the railway line during week commencing 2 December and take two weeks to complete. When we are tunnelling directly under the railway tracks, we will be carrying out 24-hour working, and this will be done between 9 -11 December 2019. There may be additional noise and lighting during this night working and we apologise for any inconvenience caused. The tunnel machine will start on the Renard Rise side.

Start date

25 Nov 2019

Two-way traffic lights

Two-way traffic lights

To allow the quick and safe delivery of equipment and materials we will have temporary two-way traffic lights, which will only be in place when the deliveries are happening.

  • Roads effected:
  • Ebley Road

There are currently no disruptions

There are currently no disruptions

map

Archaeological findings

This area produced multiple agricultural features and significant quantities of Iron Age and in particular, Roman pottery.

How are we doing?

If you have any feedback about our works, please click the button below.

Why are we doing this?

young boy washing face or drinking water from running tap

Meet the team

Amanda Hales

Amey Customer Service Officer