Stroud Resilience Project

We’re investing £11 million to make Stroud’s drinking water supply even more resilient for the future

Our progress so far

IN PROGRESS - 28 FEB 2020

Progress - 99%

Start date

17 September 2018

Work completed

Work in Progress

We have laid about 4.5km of water main so far, work is prgressing well.

Upcoming work

Estimated completion date

28 February 2020

COMPLETE - 27 MAR 2020

Complete - 100%

Start date

25 November 2019

Work completed

Ebley Road
During week commencing 25 November 2019, we will begin to construct the pit adjacent to 22 & 23 Renard Rise and this should take approximately one week to complete. The sound proof panels will be placed on the fencing. We plan to commence the tunnelling under the railway line during week commencing 2 December and take two weeks to complete. When we are tunnelling directly under the railway tracks, we will be carrying out 24-hour working, and this will be done between 9 -11 December 2019. There may be additional noise and lighting during this night working and we apologise for any inconvenience caused. The tunnel machine will start on the Renard Rise side.

Work in Progress

Ebley Road
This week we plan to lay the new water pipe between the railway line and Ebley Road and take two - three weeks to complete. Following this final work we begin the reinstatement of the land where we've already worked.

Upcoming work

Estimated completion date

27 March 2020

COMPLETE - 3 NOV 2019

Complete - 100%

Start date

26 October 2019

Work completed

This phase of our works was completed between 26 October and 3 November 2019.

Work in Progress

Upcoming work

Estimated completion date

3 November 2019

IN PROGRESS - JULY 2020

In Progress - 93%

Start date

14 October 2019

Work completed

Playground area
We plan to remove the playground in equipment during week commencing 14 October 2019. Following this we will start the preparation works in the green open space opposite properties 11 to 13 and 19 to 23 Renard Rise. We will create an access off Ebley Road and securely fence the working area. We will then remove the topsoil and store it on site. All equipment and materials will be delivered to the site from Ebley Road and we will have temporary traffic lights in place during these deliveries. Part of the scheme involves constructing the new water main under the railway line and this will be done using a tunnelling technique. In early November we will start the construction of the pits for the tunnel machine and these should take approximately four weeks to construct. We plan to commence the tunnelling under the railway line in early December and take approximately 10 days to complete.

Work in Progress

All the pipe has been laid and we are carrying out the final parts of reinstating the land. The new playground equipment is due to be installed in June 2020 and the area will be ready for July 2020.

Upcoming work

Estimated completion date

July 2020

COMPLETE - 1 JUN 2019

Complete - 100%

Start date

19 May 2019

Work completed

Stroud Naivigation Canal
Stroud Navigation Canal, footpath closure started this week until 1 June 2019. Glocs have proposed an alternative route when the towpath is closed and this is along Ebley Road.

Work in Progress

Upcoming work

Estimated completion date

1 June 2019

COMPLETE - 2 AUG 2019

Complete - 100%

Start date

28 May 2019

Work completed

Broad Street
This phase of our works will begin on 28 May for 10 weeks. Broad Street closure will start from 28 May 2019 and ST are providing alternative transport arrangements for the bus stops which will no longer be operational during the 10 week closure. We have been liaising with the Parish Council and Selsley Community Group and they are all aware of and happy with our alternative transport arrangement, especially for the elderly.

Work in Progress

Upcoming work

Estimated completion date

2 August 2019

COMPLETE - 5 APR 2019

Complete - 100%

Start date

11 March 2019

Work completed

Selsey Road
We are currently laying the new water pipeline in the fields north of the village of North Woodchester and will shortly be reaching Selsley Road. We plan from 11 March 2019, under a road closure, to lay the new pipe along a section of this road and take approximately four weeks to complete this section. We will then move back into private land and continue installing the new pipeline to the south of North Woodchester.

Work in Progress

Upcoming work

Estimated completion date

5 April 2019

COMPLETE - 4 MAR 2019

Complete - 100%

Start date

18 February 2019

Work completed

Beacon Lane
We have just laid the new water pipe across Beacon Lane. From 4 March we will cross Horsemarling Lane with the new pipeline and to carry this out quickly and safely there will be a day time road closure in place between the hours of 9:30hrs and 15:30hrs.

Work in Progress

Upcoming work

Estimated completion date

4 March 2019

COMPLETE - 29 MAR 2019

Complete - 100%

Start date

18 March 2019

Work completed

Oxlynch Lane
During week commencing 18 March we plan to install the new water pipeline across Oxlynch Lane, Standish. Again we will implement a day time road closure, between the hours of 9:30hrs and 15:30hrs. We anticipate this crossing approximately three days to complete.

Work in Progress

Upcoming work

Estimated completion date

29 March 2019

COMPLETE - 15 MAR 2019

Complete - 100%

Start date

4 March 2019

Work completed

Horsemarling Lane
We have just laid the new water pipe across Beacon Lane. From 4 March we will cross Horsemarling Lane with the new pipeline and to carry this out quickly and safely there will be a day time road closure in place between the hours of 9:30hrs and 15:30hrs.

Work in Progress

Upcoming work

Estimated completion date

15 March 2019

Map of water main replacement in Stroud area

Taking care of one of life's essentials

Archaeological findings

This area produced multiple agricultural features and significant quantities of Iron Age and in particular, Roman pottery.