Southcreast, Redditch

We’re committed to reducing the risk of flooding and improving water quality in the natural environment. This work will enable us to significantly reduce the risk of sewer flooding in the Southcrest area.

Our progress so far

UPCOMING - 22 JUN 2020

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place on Tunnel Drive.

Roads affected:

Tunnel Drive

Progress - 0%

Start date

22 June 2020

Work completed

Work in Progress

Upcoming work

We’ll be laying approximately 1100 metres of new surface water sewers and constructing new storage tanks adjacent to Tunnel Drive. We’ll also be repairing and replacing some of the existing sewer network in the area.

Estimated completion date

12 October 2020

UPCOMING - 23 JUN 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Parsons Road to Sycamore Avenue

Progress - 0%

Start date

23 June 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

29 July 2020

UPCOMING - 30 JUL 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Parsons Road to the Mayfields

Progress - 0%

Start date

30 July 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

7 October 2020

UPCOMING - 1 OCT 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Parsons Road

Progress - 0%

Start date

1 October 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

9 December 2020

UPCOMING - 8 OCT 2020

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place

Roads affected:

Sycamore Avenue

Progress - 0%

Start date

8 October 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

25 November 2020

UPCOMING - 25 NOV 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Myrtle Avenue

Progress - 0%

Start date

25 November 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

19 January 2021

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

The Mayfields (from Parsons Road)

Progress - 0%

Start date

10 December 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

3 February 2021

Road closure

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

The Mayfields (from Sycamore Ave)

Progress - 0%

Start date

4 February 2021

Work completed

Work in Progress

Upcoming work

Estimated completion date

20 April 2021

UPCOMING - 19 JAN 2021

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Greenfields

Progress - 0%

Start date

19 January 2021

Work completed

Work in Progress

Upcoming work

Estimated completion date

23 April 2021

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Trudie Thomas

Mott MacDonald Bentley Customer Liaison Manager

01952 468832