In My Area

Southcrest, Redditch

We’re committed to reducing the risk of flooding and improving water quality in the natural environment. This work will enable us to significantly reduce the risk of sewer flooding in the Southcrest area.

Our progress so far

IN PROGRESS

Road Closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Myrtle Avenue

Progress - 40%

Start date

4 January 2021

Upcoming work

Work in Progress

The team are currently working on Myrtle Avenue under a road closure.

Work completed

Estimated completion date

26 February 2021

Road Closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Parsons Road to the Mayfields

Progress - 0%

Start date

15 February 2021

Upcoming work

Work in Progress

The team started work on Parsons Road on 15 February 2021 under a road closure

Work completed

Estimated completion date

2 April 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Greenfields

Progress - 0%

Start date

21 February 2021

Upcoming work

Work in Progress

Our team will begin work in Greenfields on 21 February 2021 under a road closure.

Work completed

Estimated completion date

1 April 2021

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

The Mayfields - Sycamore Ave to Mount Pleasant

Progress - 0%

Start date

30 April 2021

Upcoming work

The team will begin work in Mayfields on 30 April with traffic lights in place.

Work in Progress

Work completed

Estimated completion date

25 June 2021

Road Closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Parson Road - Mount Pleasant to Tunnel Drive

Progress - 0%

Start date

30 April 2021

Upcoming work

The team will start work in Parsond Road on 30 April 2021 working under a road closure.

Work in Progress

Work completed

Estimated completion date

18 June 2021

Road Closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

The Mayfields - Parsons Road to Sycamore Avenue

Progress - 0%

Start date

19 March 2021

Upcoming work

The team will start wotk in the Mayfields on 19 March 2021 working under a road closure.

Work in Progress

Work completed

Estimated completion date

30 April 2021

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Trudie Thomas

Mott MacDonald Bentley Customer Liaison Manager

01952 468832