Southcrest, Redditch

We’re committed to reducing the risk of flooding and improving water quality in the natural environment. This work will enable us to significantly reduce the risk of sewer flooding in the Southcrest area.

Our progress so far

Progress - 30%

Start date

22 June 2020

Upcoming work

Over the next 4 weeks we will be installing the 1.5m dia. section of the surface water storage on Tunnel Drive, completing the installation of the sewer storage tank in Mayfields Carpark and continuing the drainage works on Parsons Road.


Bird nesting delay
The bird nesting by Tunnel Drive car park has delayed the works on the sewage water tank. The connection to the tank was not possible as the pipework runs right under the tree that had the bird nesting. As for the moment the bird is no
longer present and a tree surgent has been called to site and will be
attending site on 7 October 2020.

Work in Progress

Tarmacking on Tunnel Drive started on 5 October 2020.


In addition to this we have also started scanning and marking up at the bottom of Parsons Road. It is still very early days therefore we will be able to update you
with proper progress by the end of July.


The road closure on Tunnel Drive/Parsons Road started on 22 June 2020 and we are on track to complete the works in this section by 12 October 2020.
The two way traffic lights on Parsons Road are on the first phase and will be
an ever presence until all three phases are complete on 09 December 2020 taking 200m of Parsons Road at a time.

Work completed

The surface water tank has been installed and all the connections have been completed.


All the manholes (surface water tank) have been completed and manhole covers installed.


Sewage tank: all the excavations have been completed and the shoring has been installed. one section of the tank has been installed and the second sections have been delivered to site. 


The work on Tunnel Drive is now complete and the road has been re-opened

Estimated completion date

12 October 2020

UPCOMING - 23 JUN 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Parsons Road to Sycamore Avenue

Progress - 0%

Start date

23 June 2020

Upcoming work

Work in Progress

Work completed

Estimated completion date

29 July 2020

UPCOMING - 30 JUL 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Parsons Road to the Mayfields

Progress - 0%

Start date

30 July 2020

Upcoming work

Work in Progress

Work completed

Estimated completion date

7 October 2020

IN PROGRESS

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Parsons Road

Progress - 0%

Start date

1 October 2020

Upcoming work

Work in Progress

Progress is going well on Parsons Road but unfortunately due to the Tunnel Drive delay this means we are currently 4 weeks behind.

Work completed

Estimated completion date

9 December 2020

IN PROGRESS

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place

Roads affected:

Sycamore Avenue

Progress - 0%

Start date

8 October 2020

Upcoming work

Work in Progress

Sycamore Avenue is now closed with a diversion in place and will re-open on 18 December 2020.

Work completed

Estimated completion date

18 December 2020

UPCOMING - 25 NOV 2020

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

Myrtle Avenue

Progress - 0%

Start date

25 November 2020

Upcoming work

Work in Progress

Work completed

Estimated completion date

19 January 2021

Traffic Lights

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

The Mayfields (from Parsons Road)

Progress - 0%

Start date

10 December 2020

Upcoming work

Work in Progress

Work completed

Estimated completion date

3 February 2021

Road closure

To allow us to complete this work quickly and safely we will have traffic lights in place.

Roads affected:

The Mayfields (from Sycamore Ave)

Progress - 0%

Start date

4 February 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

20 April 2021

UPCOMING - 19 JAN 2021

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place.

Roads affected:

Greenfields

Progress - 0%

Start date

19 January 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

23 April 2021

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Trudie Thomas

Mott MacDonald Bentley Customer Liaison Manager

01952 468832