In My Area

Shawbirch Road

We’re carrying out some vital improvement work by installing a new water main through Wrockwardine, in private land and along Shawbirch Road for the new development site.

Our progress so far

Complete - 100%

Start date

20 July 2020

Upcoming work

Work in Progress

Work completed

We have now completed this phase of the works.

Estimated completion date

10 August 2020

Complete - 100%

Start date

10 August 2020

Upcoming work

Work in Progress

Work completed

We have now completed phase one of the works.

Estimated completion date

6 September 2020

Complete - 100%

Start date

21 September 2020

Upcoming work

Work in Progress

Work completed

Work is now complete and the road c,losure was removed on Friday 13 November. We would like to thank all the residents and businesses for their patience.

Estimated completion date

13 November 2020

What we're doing

Working under the supervision of Network Rail. The workers and Site Manager are checking the new meter and valve set up before commissioning the new section of water pipe from Phase 1 in Wrockwardine village.

Taking care of one of life's essentials

Ask us a question

Unfortunately due to the situation with Covid-19 we are unable to run our usual drop in session for these works. If you have any questions relating to this work, please use the button below and we'll get back to you.

Meet the team

Sarah Miles

Amey Customer Service Officer

07716 227712