Roston Drive, Hinckley - Roston Drive, Hinckley

70%

In progress

28 Sep 2018

Estimated completion date
Upcoming work
Work in progress
Normandy Road sewer scheme

Following our previous update we've encountered further difficulties and delays due to ground conditions. The risk associated with continuing to use the drilling method to try and install the new pipe is too great and we've decided not to proceed with this method, We shall remove all our equipment, reinstate our working areas and re-open Roston Drive to two way traffic by 22 December 2017. Hopefully work will restart using a different technique in Spring of 2018.

Work completed
Start date

16 Jul 2018

Road closure and traffic management

Road closure and traffic management

Our start date for this work was delayed by the water main repair on Roston Drive. We have suffered further delays due to unforeseen obstructions in the ground through which we are drilling. The revised planned completion date for our work is 24th November 2017

  • Roads effected:
  • Brascote Road and Roston Drive

Bus stop suspended

Bus stop suspended

The bus stop opposite Brascote Road will be suspended for the duration of the works, however the bus stop a short distance to the east along Roston Drive will remain open.

  • Routes effected:
  • The bus stop opposite Brascote Road

There are currently no disruptions

Why are we doing this?

Meet the team

Paul Petherick

Project Engineer - NMC

Stephan Read

Project Manager

Kevin Bowen

Severn Trent - Programme Engineer

STWater Twitter

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages