Polesworth to Dordon

We're carrying out water pipe improvements in Leicestershire to secure water supplies for the future

Our progress so far

IN PROGRESS - 2 MAR 2020

Progress - 45%

Start date

13 January 2020

Upcoming work

We're replacing the existing water pipes in your area for new ones.

Work in Progress

Work completed

Estimated completion date

2 March 2020

IN PROGRESS - 31 MAY 2020

Progress - 80%

Start date

16 March 2020

Upcoming work

We're replacing the existing water pipes in your area for new ones.

Work in Progress

Work completed

Estimated completion date

12 July 2020