Norton, Ludlow - Phase 10 & 11 - Back Lane/Back Lane to Onibury

50%

In progress

05 Mar 2019

Estimated completion date
Upcoming work
Work in progress
Phase 11

Phase 11 is due to start 11 February 2019. There will be no way through off the A49 into Onibury village, please follow diversion in place. We would like to thank you for your patience and understanding during these works.

Phase 10

Phase 10 is almost complete and Phase 11 due to start on Monday 11 February 2019. At that time, there will be no through road into Onibury from the A49. Please follow diversions in place. We apologise for any inconvenience and thank you for your patience and understanding.

Work completed
Start date

04 Feb 2018

Road closure

Road closure

To allow us to carry out this work quickly and safely, works will be undertaken with the use of multiway lights on the Corvedale road section. There will be road closures with diversion routes, for each section throughout the rest of the project. We expect the work to take around 12 months to complete.

  • Roads effected:
  • Back Lane, Back Lane to Onibury and Onibury toward Norton

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Meet the team

Samantha Pedley

Amey Customer Liaison Officer

STW Twitter

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages