Minton Street, Stoke-on-Trent - Hall Place

100%

Complete

30 Apr 2018

Estimated completion date
Upcoming work
Work in progress
Work completed
Hall Place

Reinstatement works at Hall Place and Minton Street have taken place this week, works will continue to install the new water pipes along Bristol Street starting week commencing 19/03/18 this section of work is expected to last around three weeks.

Hall Place

Works continue to progress well along Minton Street and Hall Place, most the new water main is now in place, work will continue during next week. Reinstatement of the excavations will continue as we progress.

Start date

29 Jan 2018

Road closure

Road closure

  • Roads effected:
  • Hall Place

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Meet the team

Steve Coventry

Amey Customer Liaison Officer

Dave Kiernan

Programme Engineer - Severn Trent

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages