In My Area

Planned improvements

Market Harborough - Phase Two

100%

Complete

31 Aug 2019

Estimated completion date
Upcoming work
Work in progress

The pipe has been laid and we're doing our final tests on the pipe

Work completed

We will be laying the final stretch of pipe on Kettering Road from Jordan Close to Bellfields Lane. To keep you and our team safe we will need to close this section of road from 2 July 2019 for three weeks

As we get to the end of laying the pipe on Kettering road, we will move onto the public footpath inbetween Kettering Road and Rockingham Road from 28 June 2019. You will see the council along the footpath at the start of the week trimming back trees before our work starts

Kettering road will be closed from the junction of Jordan Close to Gorse Lane from 28 June 2019 until 4 July 2019

Work has started on Kettering Road and we'll be working to the junction of Ashley Way until the Middle of May. So we can keep you and our team safe, we will need to carry out this section of work using a one way road closure, traffic lights, Barriers and Signs

Our work is progressing along Kettering Road quickly you will see the one way road closure move with us. From the middle of May you will see us moving past the junction of Ashley Way and working towards Gores Lane

Start date

29 Apr 2019

To allow us to carry out this work safely we’ve agreed with the local authority to slow down the flow of traffic using road closures, traffic lights and some priority signage and barriers. Access to properties, and pedestrians will be maintained and a diversion route will be in place.

  • Roads effected:
  • Kettering Road

There are currently no disruptions

There are currently no disruptions

supply map

Latest photos of our work

Why are we doing this?

Meet the Team

lisa orme picture

Lisa Orme

Community Communications Officer

How are we doing?

If you have any feedback about our works, please click the button below.