Main Street, Calver - Main Street, Calver

50%

In progress

31 Jan 2019

Estimated completion date
Upcoming work
Work in progress

Work will start week commencing 19 November at the bottom of Donkey Road and the team will work their way towards the A623 Kingsgate/Baslow Road by January 2019.

Work completed
Start date

19 Nov 2018

Road closure

Road closure

Due to the location of the pipe, and to keep you and our workforce safe, we have agreed with the local authority to close Main Street to through traffic for 10 weeks whilst the work is taking place. We may also need residents to park further down the road as the work progresses.

  • Roads effected:
  • Main Street

There are currently no disruptions

Parking

Parking

We may need residents to park further down the road as the work progresses.

  • Locations effected:

Why are we doing this?

Meet the team

Rachel Lowe

Community Communications Officer - Severn Trent Water

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages