Littlemoor Lane - Main Street Junction

100%

First phase

11 Jun 2019

Estimated completion date
Upcoming work
Work in progress
Work completed
Phase three - Sherwood Street

We'll be starting phase three of our scheme around 18 May 2019 on Sherwood Street and will finish in June 2019.

Phase one - Main Street Junction

Phase one of our scheme is due to start on 13 April 2019 for approximately two weeks.

Phase two - Littlemoor Lane

We'll be starting phase two of our scheme around 27 April 2019. We’ll work our way down Littlemoor Lane until we reach Newtonwood Lane.

Start date

13 Apr 2019

Temporary traffic lights

Temporary traffic lights

During this job we’ll be using traffic lights to keep you and our teams safe and complete the work as quickly as possible. We’re really sorry about any nuisance we cause during this essential work.

  • Roads effected:
  • Main Street Junction, Littlemoor Lane, Sherwood Street

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Meet the team

Roisin McBain

Community Comms Officer

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages