In My Area

Langley Mill

Every so often, we need to replace old water pipes due to leaks and bursts. So we're investing around £3 million on the water pipe network in Langley Mill to upgrade the pipes in this area.

Our progress so far

The work will be completed by three teams and will start from week commencing 17 May 2021 on the following: Cromford Road, Argyle Street and Elnor Street. Once these are complete, the team will move from street to street replacing the water pipes, the whole scheme will take approximately thirteen months to be complete.

IN PROGRESS

Two-way traffic lights

In order to keep you and our workforce safe, we’ll need to complete the work with two-way traffic lights in place.

Roads affected:

Cromford Road

Our Progress

Start date

2 August 2021

Upcoming work

Work in Progress

All the pipe has been laid on Cromford Road, the team started work on 4 October to makie the final connections. Once the finla connections have been made they will then abandon the old water pipe.

We will be using two-way traffic lights whilest this work is ongoing and it should take four weeks to complete.

Work completed

Estimated completion date

3 November 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working on Station Road and Wesley Street.

Roads affected:

Station Road and Wesley Street

Our Progress

Start date

9 August 2021

Upcoming work

Work in Progress

To enable us to progress our work as quickly as possible, we're working over the weekends on Station Road. The team will be working from 9am to 5pm on a Saturday and 10am to 4pm on a Sunday.

Work completed

Estimated completion date

January 2022

COMPLETE

Our Progress

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

6 June 2021

COMPLETE

Our Progress

Start date

Mid June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

7 June 2021

COMPLETE

Our Progress

Start date

14 June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

26 June 2021

COMPLETE

Our Progress

Start date

14 June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

26 June 2021

COMPLETE

Our Progress

Start date

12 July 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

25 July 2021

IN PROGRESS

Our Progress

Start date

26 May 2021

Upcoming work

All the pipe has been laid on Dean Street, the team will be returning to complete finla connections on the 18 October and the work should take about a week to complete.

Work in Progress

Work completed

Estimated completion date

7 June 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place. 

Roads affected:

Sedgewick Street

Our Progress

Start date

25 October 2021

Upcoming work

Our team will start work on Sedgewick Street on 25 October, so we can work as quickly as possible we ask you to make sure the area is clear of parked cars.

Work in Progress

Work completed

Estimated completion date

TBC

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Bridge Street

Our Progress

Start date

28 June 2021

Upcoming work

Work in Progress

All the pipe has been laid on Bridge Street, the team will be returning to complete finla connections on the 18 October and the work should take about a week to complete.

Work completed

Estimated completion date

12 July 2021

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

Early September 2021

COMPLETE

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

Early August 2021

COMPLETE

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

Early August 2021

COMPLETE

Our Progress

Start date

23 August 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

Late September 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Hampden Street

Our Progress

Start date

1 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

14 November 2021

COMPLETE

Our Progress

Start date

September 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

October 2021

IN PROGRESS

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Ash Mount Road

Our Progress

Start date

4 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

25 October 2021

IN PROGRESS

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Peel Street

Our Progress

Start date

4 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

25 October 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Pine Avenue

Our Progress

Start date

8 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

6 December 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Bailey Brook Drive

Our Progress

Start date

6 December 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

17 January 2022

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Hillside

Our Progress

Start date

15 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late November 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Turton Close

Our Progress

Start date

22 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

6 December 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Chestnut Road

Our Progress

Start date

22 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

6 December 2021

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Bailey Brook Walk

Our Progress

Start date

17 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

24 January 2022

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Horsley Crescent

Our Progress

Start date

24 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

14 February 2022

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Gregory Avenue

Our Progress

Start date

7 February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

14 February 2022

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Lower Dunstead Road

Our Progress

Start date

17 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

28 February 2022

COMPLETE

Our Progress

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

6 June 2021

COMPLETE

Our Progress

Start date

31 May 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

25 July 2021

COMPLETE

Our Progress

Start date

14 June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

28 June 2021

COMPLETE

Our Progress

Start date

2 August 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

15 August 2021

COMPLETE

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

2 August 2021

IN PROGRESS

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working on Aldreds Lane.

Roads affected:

Aldreds Lane

Our Progress

Start date

6 September 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

18 October 2021

COMPLETE

Our Progress

Start date

August 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

September 2021

Our Progress

Start date

September 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

Late September 2021

IN PROGRESS

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Oliver Close

Our Progress

Start date

4 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

11 October 2021

IN PROGRESS

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Julie Avenue

Our Progress

Start date

4 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

25 October 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Oaklands Avenue

Our Progress

Start date

18 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

15 November 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

England Crescent

Our Progress

Start date

1 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

22 November 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Holbrook Street

Our Progress

Start date

15 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

20 December 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Elmsfield Avenue

Our Progress

Start date

3 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

24 January 2022

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Holbrook Street

Our Progress

Start date

17 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

7 February 2022

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Marshall Street

Our Progress

Start date

7 February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

28 February 2022

UPCOMING

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Greenacre Avenue

Our Progress

Start date

31 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

21 February 2022

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Wentworth Croft

Our Progress

Start date

21 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

4 February 2022

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Darfield Drive

Our Progress

Start date

28 February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

21 March 2022

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Brampton Avenue

Our Progress

Start date

28 February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

21 March 2022

Taking care of one of life's essentials


Let us know how we're doing

Please get in touch if you have any feedback about our works.


Meet the team

Lisa Orme

Severn Trent Communications Officer

07790 845234