In My Area

Langley Mill

Every so often, we need to replace old water pipes due to leaks and bursts. So we're investing around £3 million on the water pipe network in Langley Mill to upgrade the pipes in this area.

Our progress so far

The work will be completed by three teams and will start from week commencing 17 May 2021 on the following: Cromford Road, Argyle Street and Elnor Street. Once these are complete, the team will move from street to street replacing the water pipes, the whole scheme will take approximately thirteen months to be complete.

UPCOMING

Two-way traffic lights

In order to keep you and our workforce safe, we’ll need to complete the work with two-way traffic lights in place.

Roads affected:

Cromford Road

Progress - 0%

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid August 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working on Station Road and Wesley Street.

Roads affected:

Station Road and Wesley Street

Progress - 0%

Start date

Mid August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

January 2022

UPCOMING

Road Closure

In order to keep you and our workforce safe, we’ll need to complete the work under a road closure.

Roads affected:

Argyle Street

Progress - 0%

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid June 2021

UPCOMING

Road Closure

In order to keep you and our workforce safe, we’ll need to complete the work under a road closure.

Roads affected:

Bank Street

Progress - 0%

Start date

Mid June 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late June 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure. 

Roads affected:

Campbell Street

Progress - 0%

Start date

Mid June 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early July 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure. 

Roads affected:

Gladstone Street

Progress - 0%

Start date

Late June 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid July 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure. 

Roads affected:

Queen Street

Progress - 0%

Start date

Mid July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late July 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place. 

Roads affected:

Dean Street

Progress - 0%

Start date

Late July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid August 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place. 

Roads affected:

Sedgewick Street

Progress - 0%

Start date

Mid August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late August 2021

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Bridge Street

Progress - 0%

Start date

Late August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid September 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Elnor Street

Progress - 0%

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid June 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Milnhay Road

Progress - 0%

Start date

Late May 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late July 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place. 

Roads affected:

Towson Avenue

Progress - 0%

Start date

Late July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid August 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Lime Avenue

Progress - 0%

Start date

Early August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid August 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Brookvale Road

Progress - 0%

Start date

Mid August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late August 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working on Aldreds Lane.

Roads affected:

Aldreds Lane

Progress - 0%

Start date

Late August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early October 2021

Taking care of one of life's essentials


Let us know how we're doing

Please get in touch if you have any feedback about our works.


Meet the team

Lisa Orme

Severn Trent Communications Officer

07790 845234