In My Area
Our progress so far
The work will be completed by three teams and will start from week commencing 17 May 2021 on the following: Cromford Road, Argyle Street and Elnor Street. Once these are complete, the team will move from street to street replacing the water pipes, the whole scheme will take approximately thirteen months to be complete.
COMPLETE
Our Progress
Start date
2 August 2021
Upcoming work
Work in Progress
Work completed
Work is now complete on this section.
Estimated completion date
3 November 2021
IN PROGRESS
Multi-way traffic lights
The team will need to work under multi-way traffic lights whilst working on Station Road and Wesley Street.
Roads affected:
Station Road and Wesley Street
Our Progress
Start date
9 August 2021
Upcoming work
Work in Progress
To enable us to progress our work as quickly as possible, we're working over the weekends on Station Road. The team will be working from 9am to 5pm on a Saturday and 10am to 4pm on a Sunday.
Work completed
Estimated completion date
14 February 2022
UPCOMING
Multi-way traffic lights
The team will need to work under multi-way traffic lights whilst working on Mansfield Road.
Roads affected:
Mansfield Road
Our progress
Start date
14 February 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
25 April 2022
COMPLETE
Our Progress
Start date
17 May 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
6 June 2021
COMPLETE
Our Progress
Start date
Mid June 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
7 June 2021
COMPLETE
Our Progress
Start date
14 June 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
26 June 2021
COMPLETE
Our Progress
Start date
14 June 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
26 June 2021
COMPLETE
Our Progress
Start date
12 July 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
25 July 2021
COMPLETE
Our Progress
Start date
26 May 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
7 June 2021
COMPLETE
Our Progress
Start date
25 October 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
TBC
COMPLETE
Our Progress
Start date
28 June 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
12 July 2021
COMPLETE
Our Progress
Start date
19 July 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
Early September 2021
COMPLETE
Our Progress
Start date
19 July 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
Early August 2021
COMPLETE
Our Progress
Start date
19 July 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
Early August 2021
COMPLETE
Our Progress
Start date
23 August 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
Late September 2021
COMPLETE
Our Progress
Start date
1 November 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
14 November 2021
COMPLETE
Our Progress
Start date
September 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
October 2021
COMPLETE
Our Progress
Start date
4 October 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
25 October 2021
COMPLETE
Our Progress
Start date
4 October 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
25 October 2021
COMPLETE
Our Progress
Start date
8 November 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
6 December 2021
COMPLETE
Our Progress
Start date
17 January 2022
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
24 January 2022
UPCOMING
Signs and Barriers
To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.
Hillside
Our Progress
Start date
14 February 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
28 February 2022
UPCOMING
Signs and Barriers
To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.
Turton Close
Our Progress
Start date
7 February 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
21 February 2022
COMPLETE
Our Progress
Start date
22 November 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
6 December 2021
IN PROGRESS
Signs and Barriers
To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.
Bailey Brook Walk
Our Progress
Start date
17 January 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
24 January 2022
IN PROGRESS
Road Closure
To allow us to complete this work quickly and safely, our team will be working with a road closure in place.
Horsley Crescent
Our Progress
Start date
24 January 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
14 February 2022
UPCOMING
Multi-way traffic lights
The team will need to work under multi-way traffic lights whilst working in this area.
Roads affected:
Gregory Avenue
Our Progress
Start date
7 February 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
14 February 2022
UPCOMING
Multi-way traffic lights
The team will need to work under multi-way traffic lights whilst working in this area.
Roads affected:
Lower Dunstead Road
Our Progress
Start date
14 February 2022
Upcoming work
We’ll need to close a section of the road between the junctions with Ashmount Road and Pine Avenue from Saturday 19th February to Sunday 27th February (school holidays).
The diversion route will be via Station Road and Cromford Road, and vice versa. To ensure that diverted vehicles do not use inappropriate alternative routes, during this time the junctions of Godkin Drive and Andrews Drive with Upper Dunstead Road will also be physically closed. We’re sorry for the inconvenience this will cause to residents who live in the Gregory Avenue area, but this is to ensure the appropriate diversion route is followed.
Work in Progress
Work completed
Estimated completion date
Late March 2022
COMPLETE
Our Progress
Start date
17 May 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
6 June 2021
COMPLETE
Our Progress
Start date
31 May 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
25 July 2021
COMPLETE
Our Progress
Start date
14 June 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
28 June 2021
COMPLETE
Our Progress
Start date
2 August 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
15 August 2021
COMPLETE
Our Progress
Start date
19 July 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
2 August 2021
COMPLETE
Our Progress
Start date
6 September 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
18 October 2021
COMPLETE
Our Progress
Start date
August 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
September 2021
COMPLETE
Our Progress
Start date
September 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
Late September 2021
COMPLETE
Our Progress
Start date
4 October 2021
Upcoming work
Work in Progress
Work completed
Estimated completion date
11 October 2021
COMPLETE
Our Progress
Start date
4 October 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
25 October 2021
COMPLETE
Our Progress
Start date
18 October 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
15 November 2021
COMPLETE
Our Progress
Start date
1 November 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
22 November 2021
COMPLETE
Our Progress
Start date
15 November 2021
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
20 December 2021
COMPLETE
Our Progress
Start date
3 January 2022
Upcoming work
Work in Progress
Work completed
The team have now completed this section of the work.
Estimated completion date
24 January 2022
UPCOMING
Road Closure
To allow us to complete this work quickly and safely, our team will be working under a road closure.
Holbrook Street
Our Progress
Start date
28 February 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
21 March 2022
UPCOMING
Road Closure
To allow us to complete this work quickly and safely, our team will be working under a road closure.
Marshall Street
Our Progress
Start date
28 February 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
21 March 2022
UPCOMING
Multi-way traffic lights
The team will need to work under multi-way traffic lights whilst working in this area.
Roads affected:
Greenacre Avenue
Our Progress
Start date
31 January 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
28 February 2022
UPCOMING
Signs and Barriers
To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.
Wentworth Croft
Our Progress
Start date
24 January 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
7 February 2022
UPCOMING
Signs and Barriers
To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.
Darfield Drive
Our Progress
Start date
10 Janaury 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
31 March 2022
IN PROGRESS
Signs and Barriers
To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.
Brampton Avenue
Our Progress
Start date
10 January 2022
Upcoming work
Work in Progress
Work completed
Estimated completion date
24 January 2022
Taking care of one of life's essentials
Securing your supply
Thirteen months in the works
£3 million investment
Let us know how we're doing
Please get in touch if you have any feedback about our works.
Meet the team
Lisa Orme
Severn Trent Communications Officer
07790 845234