In My Area

Langley Mill

Every so often, we need to replace old water pipes due to leaks and bursts. So we're investing around £3 million on the water pipe network in Langley Mill to upgrade the pipes in this area.

Our progress so far

The work will be completed by three teams and will start from week commencing 17 May 2021 on the following: Cromford Road, Argyle Street and Elnor Street. Once these are complete, the team will move from street to street replacing the water pipes, the whole scheme will take approximately thirteen months to be complete.

IN PROGRESS

Two-way traffic lights

In order to keep you and our workforce safe, we’ll need to complete the work with two-way traffic lights in place.

Roads affected:

Cromford Road

Our Progress

Start date

17 May 2021

Upcoming work

To enable us to progress our work past your home or business and complete as quickly as possible, we’ll be starting to work over the weekends on Cromford Road from 5 June 2021. The team will be working from 9am until 5pm on a Saturday and 10am until 4pm on a Sunday. Please note that the team may finish a little earlier due to what job needs to be done on the day.

Work in Progress

Work completed

Estimated completion date

Mid August 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working on Station Road and Wesley Street.

Roads affected:

Station Road and Wesley Street

Our Progress

Start date

9 August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

January 2022

COMPLETE

Our Progress

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

6 June 2021

COMPLETE

Our Progress

Start date

Mid June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

7 June 2021

COMPLETE

Our Progress

Start date

14 June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

26 June 2021

COMPLETE

Our Progress

Start date

14 June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

26 June 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Roads affected:

Queen Street

Our Progress

Start date

12 July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

25 July 2021

COMPLETE

Our Progress

Start date

26 May 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

7 June 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place. 

Roads affected:

Sedgewick Street

Our Progress

Start date

9 August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

22 August 2021

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Bridge Street

Our Progress

Start date

28 June 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

12 July 2021

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

North Street / Eastview Terrace

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early September 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

West Street

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early August 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Orchard Street

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early August 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Thompson Street

Our Progress

Start date

23 August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late September 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Hampden Street

Our Progress

Start date

6 September 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

13 September 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Ebenezer Street

Our Progress

Start date

September 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

October 2021

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Ash Mount Road

Our Progress

Start date

October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

November 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Peel Street

Our Progress

Start date

October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

November 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Pine Avenue

Our Progress

Start date

October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

November 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Bailey Brook Drive

Our Progress

Start date

November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid December 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Hillside

Our Progress

Start date

November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late November 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Turton Close

Our Progress

Start date

November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late November 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Chestnut Road

Our Progress

Start date

November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late November 2021

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signs and barriers in place.

Bailey Brook Walk

Our Progress

Start date

December 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Mid December 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working with a road closure in place.

Horsley Crescent

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

February 2022

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Gregory Avenue

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late January 2022

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Lower Dunstead Road

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late February 2022

COMPLETE

Our Progress

Start date

17 May 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

6 June 2021

IN PROGRESS

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Milnhay Road

Our Progress

Start date

31 May 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

25 July 2021

COMPLETE

Our Progress

Start date

14 June 2021

Upcoming work

Work in Progress

Work completed

The team have now completed this section of the work.

Estimated completion date

28 June 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Lime Avenue

Our Progress

Start date

2 August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

15 August 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Brookvale Road

Our Progress

Start date

19 July 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

2 August 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working on Aldreds Lane.

Roads affected:

Aldreds Lane

Our Progress

Start date

Late August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early October 2021

UPCOMING

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Amber Drive

Our Progress

Start date

August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

September 2021

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Rosewood Crescent

Our Progress

Start date

September 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late September 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Oliver Close

Our Progress

Start date

September 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late September 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Julie Avenue

Our Progress

Start date

Late September 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late October 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Oaklands Avenue

Our Progress

Start date

October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

November 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

England Crescent

Our Progress

Start date

November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

Early December 2021

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Holbrook Street

Our Progress

Start date

November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

December 2021

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Elmsfield Avenue

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

February 2022

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Holbrook Street

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

February 2022

UPCOMING

Road Closure

To allow us to complete this work quickly and safely, our team will be working under a road closure.

Marshall Street

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

February 2022

UPCOMING

Multi-way traffic lights

The team will need to work under multi-way traffic lights whilst working in this area.

Roads affected:

Greenacre Avenue

Our Progress

Start date

January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

February 2022

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Wentworth Croft

Our Progress

Start date

February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

Late February 2022

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Darfield Drive

Our Progress

Start date

February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

March 2022

UPCOMING

Signs and Barriers

To allow us to complete this work quickly and safely, our team will be working with signa and barriers in place.

Brampton Avenue

Our Progress

Start date

February 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

March 2022

Taking care of one of life's essentials


Let us know how we're doing

Please get in touch if you have any feedback about our works.


Meet the team

Lisa Orme

Severn Trent Communications Officer

07790 845234