In My Area

Kidsgrove

We plan to start water main renewals in Kidsgrove in May 2020 and complete in September 2020.

Covid-19

These works have been classed as essential work by the UK Government. We are following the Government advice closely and our team of Key workers are working to the current guidance. If we consider that we need to change the way in which we are carrying out the work, then we will amend our plan and programme accordingly.  

We now have a confirmed start date of 4 May 2020. To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the first phase of renewing our water mains will be in The Mount.

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Our progress so far

COMPLETE

Complete - 100%

Start date

4 May 2020

Upcoming work

Work in Progress

Work completed

Work has now completed in The Mount

Estimated completion date

15 May 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the second phase of renewing our water mains will be in Market Street.

Complete - 100%

Start date

18 May 2020

Upcoming work

Work in Progress

Work completed

Work has now been completed in Market Street.

Estimated completion date

6 July 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the third phase of renewing our water mains will be in Heathcote Street.

Complete - 100%

Start date

18 May 2020

Upcoming work

Work in Progress

Work completed

Work has now been completed in Heathcote Street.

Estimated completion date

6 July 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the fouth phase of renewing our water mains will be in Kinnersley Street.

Complete - 100%

Start date

6 July 2020

Upcoming work

Work in Progress

Work completed

This section of work is now complete.

Estimated completion date

12 July 2020

COMPLETE

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the fifth phase of renewing our water mains will be in Lamb Street.

Complete - 100%

Start date

13 July 2020

Upcoming work

Work in Progress

Work completed

We are pleased to confirm the section of works on Lamb Street has been completed, we intended to move onto William Street but due to a request from the school we have moved from Lamb Street directly onto Rutland Road, this to help minimise disruption to publics and parents when the school re-opens in September.

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the sixth phase of renewing our water mains will be in William Street.

Complete - 100%

Start date

26 August 2020

Upcoming work

Work in Progress

Work completed

Work is now complete in William Street, after this we will move on to King Street.

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the seventh phase of renewing our water mains will be in Rutland Road.

Complete - 100%

Start date

18 August 2020

Upcoming work

Work in Progress

Work completed

We have now completed work in Rutland Road. We are finishing work in William Street before moving on to King Street.

Estimated completion date

September 2020

COMPLETE

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the eighth phase of renewing our water mains will be in King Street.

Complete - 100%

Start date

16 September 2020

Upcoming work

Work in Progress

Work completed

Work in King Street is now complete.

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the ninth phase of renewing our water mains will be in Bedford Road.

Complete - 100%

Start date

September 2020

Upcoming work

Work in Progress

Work completed

Work in Bedford Road is now complete.

Estimated completion date

October 2020

IN PROGRESS

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the tenth phase of renewing our water mains will be in Victoria Avenue.

Road closure

To complete this work quickly and safely we will have a road closure in place from approximately 2 October 2020.

Roads affected:

Victoria Avenue

Progress - 0%

Start date

2 October 2020

Upcoming work

Work in Progress

Work has progressed well and is almost complete. We should have all excavations back filled and be clear from site by the end of the working day on 6 November 2020. We would like to thank all residents and businesses for their support and understanding during this scheme.

Work completed

Estimated completion date

6 November 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Samantha Pedley

Amey Customer Service Officer

07725 073188