In My Area

Kidsgrove

We plan to start water main renewals in Kidsgrove in May 2020 and complete in September 2020.

Covid-19

These works have been classed as essential work by the UK Government. We are following the Government advice closely and our team of Key workers are working to the current guidance. If we consider that we need to change the way in which we are carrying out the work, then we will amend our plan and programme accordingly.  

We now have a confirmed start date of 4 May 2020. To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the first phase of renewing our water mains will be in The Mount.

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Our progress so far

IN PROGRESS - 4 MAY 2020

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

The Mount

Progress - 90%

Start date

4 May 2020

Work completed

Work in Progress

Work started in the Mount on 4 May 2020 and we plan to have this section finished by 15 May 2020, we will then move on to Market Street.

Upcoming work

Estimated completion date

15 May 2020

UPCOMING - 18 MAY 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the second phase of renewing our water mains will be in Market Street.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Market Street

Progress - 0%

Start date

18 May 2020

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

TBA

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the third phase of renewing our water mains will be in Heathcote Street.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Heathcote Street

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the fouth phase of renewing our water mains will be in Kinnersley Street.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Kinnersley Street

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

UPCOMING

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the fifth phase of renewing our water mains will be in Lamb Street.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Lamb Street

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the sixth phase of renewing our water mains will be in William Street.

Traffic cone icon

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

William Street

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the seventh phase of renewing our water mains will be in Rutland Road.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Rutland Road

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

September 2020

UPCOMING

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the eighth phase of renewing our water mains will be in King Street.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

King Street

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the ninth phase of renewing our water mains will be in Bedford Road.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Bedford Road

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress.

Estimated completion date

September 2020

To allow us to carry out this work quickly and safely we will have rolling road closures in place. This is to ensure your safety and the safety of our workforce. We plan to carry out the work in phases and the tenth phase of renewing our water mains will be in Victoria Avenue.

Road closure

To complete this work quickly and safely we will have a road closure in place.

Roads affected:

Victoria Avenue

Progress - 0%

Start date

TBA

Work completed

Work in Progress

Upcoming work

We’re sorry but at this time we’re unable to give exact dates when we will be in your street, as this will depend on progress. 

Estimated completion date

September 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Samantha Pedley

Amey Customer Service Officer

07725 073188