Kenning Street, Chesterfield - Water pipe replacement work

40%

In progress

17 Aug 2018

Estimated completion date
Upcoming work
Bestwood Park

Phase three will take place in Bestwood Park during the start of July until mid July 2018.

Final phase - Bestwood Park

The final phase of our work will take place in Bestwood Park in mid July – early August 2018.

Work in progress
Phase two

Will take place during the end of June until the beginning of July 2018.

Work completed
Kenning Street, Chesterfield

The first phase of our works will begin on Kenning Street from 11 June 2018 - until the end of June 2018.

Start date

11 Jun 2018

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Meet the team

Timothy Ip

Community Communications Officer - Severn Trent

How are we doing?

If you have any feedback about our works, please click the button below.

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages