We carried out water main renewals in Honeybourne Road in 2016. Due to engineering difficulties, we were unable to complete all the work. We are starting work again from 10 August and will take 5 weeks to complete.

Our progress so far

IN PROGRESS - 10 AUG 2020

Two and Four-Way Traffic Lights

To enable us to carry out our work quickly and safely, we will have two-way traffic lights in place, this will change to four-way traffic lights once we reach the junction of Cleeve Road and Welford Road. This is to ensure your safety and the safety of our workforce.

Roads affected:

Honeybourne Road B4085

Progress - 0%

Start date

10 August 2020

Upcoming work

Work in Progress

We plan to install new valves and carry out final connections along B4085, Honeybourne Road between the Topiary Park and the junction of Cleeve Road and Welford Road.

Once completed we will commission the new water main and abandon the old one. During our work, the new water main will be chlorinated, flushed and sent off for testing. Please note there may be lack of work on site as this process takes place.

Work completed

Estimated completion date

11 September 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Simon Williams

Amey Customer Liaison Officer

07885 475321