We’re carrying out some vital improvement work by installing a new water main along Highfield Road, Lydney

Our progress so far

IN PROGRESS - 17 AUG 2020

Two-Way Traffic Lights

To allow for us to carry out this work safely and quickly, we will initially have two-way traffic lights in place and then three-way traffic lights as we move to its junction with Highfield Lane.

Roads affected:

Highfield Road

Progress - 0%

Start date

17 August 2020

Upcoming work

Work in Progress

We’re investing in our network to ensure we provide a reliable service for our customers now and in the future. So, we are installing a new water main in Highfield Road, Lydney.

We plan to start from 17 August 2020, starting in Highfield Road near to Crosshand garage moving towards its junction with Centurion Road.

Work completed

Estimated completion date

4 September 2020

Three-way Traffic Lights

To allow us to complete this work quickly and safely we will have three-way traffic lights in place at the junction of Highfield Lane.

Roads affected:

Highfield Lane and Highfield Road juntion

Progress - 0%

Start date

31 August 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

18 September 2020

Three-way Traffic Lights

To allow us to complete this work quickly and safely we will have three-way trafic lights in place at the junction of Rodley Manor Way.

Roads affected:

Highfield Road and Rodley Manor Way junction

Progress - 0%

Start date

14 September 2020

Work completed

Work in Progress

Upcoming work

Estimated completion date

9 October 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Simon Williams

Amey Customer Liaison Officer

07885 475321