A £2M investment will see Birmingham Road and other surrounding roads fitted with new water pipes, replacing ageing ones that are more prone to bursts and leaks.

Our progress so far

IN PROGRESS - 7 JUL 2020

Traffic cone icon

Road closure

So that we can carry out our works quickly and safely we will need to close the road between the junction of Birmingham Road and Old Birmingham Road

Roads effected:

Alvechurch Highway

Progress - 0%

Start date

14 April 2020

Work completed

Work in Progress

Upcoming work

We'll be starting work in the area soon to replace the old water pipes for new ones.

Estimated completion date

7 July 2020

UPCOMING - 7 MAY 2020

Traffic cone icon

Road closure

So that we can carry out our works quickly and safely we will need to close the road from the junction of Alvechurch Highway to junction of Beacon Hill.

Roads effected:

Beacon Lane

Progress - 0%

Start date

27 April 2020

Work completed

Work in Progress

Upcoming work

We'll be starting work in the area soon to replace the old water pipes for new ones.

Estimated completion date

7 May 2020

UPCOMING - 7 MAY 2020

Traffic cone icon

Road closure

So that we can carry out our works quickly and safely we will need to close the road from the junction of Alvechurch Highway to junction of Old Birmingham Rd

Roads effected:

Marlbrook Lane

Progress - 0%

Start date

27 April 2020

Work completed

Work in Progress

Upcoming work

We'll be starting work in the area soon to replace the old water pipes for new ones.

Estimated completion date

7 May 2020

UPCOMING - 20 JUL 2020

Progress - 0%

Start date

8 June 2020

Work completed

Work in Progress

Upcoming work

We'll be starting work in the area in June 2020 to replace the old water pipes for new ones.

Estimated completion date

20 July 2020

UPCOMING - 13 JUL 2020

Progress - 0%

Start date

8 June 2020

Work completed

Work in Progress

Upcoming work

We'll be starting work in the area in June 2020 to replace the old water pipes for new ones.

Estimated completion date

13 July 2020

UPCOMING - 29 AUG 2020

Progress - 0%

Start date

18 July 2020

Work completed

Work in Progress

Upcoming work

We'll be starting work in the area in July 2020 to replace the old water pipes for new ones.

Estimated completion date

29 August 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Roisin McBain

Severn Trent Community Officer

07714741935