In My Area

Hampton Road, Droitwich

We're replacing the water pipes in the Hampton Road area of Droitwich, this is to help reduce the risk of bursts and flooding.

Our progress so far

IN PROGRGESS - 27 MAR 2020

Traffic cone icon

Signs and barriers

To allow us to complete this work quickly and safely we will have road closures in place, along with signs and barriers. This is to ensure your safety and the safety of our workforce.

Roads effected:

Hampton Road

Progress - 70%

Start date

9 March 2020

Work completed

Work in Progress

Hampton Road
All of the new water pipes have now been installed. From 16 March work will
begin to connect the new pipes to customers properties and businesses, once
this is complete final reinstatement will take place. We’re currently working
to our schedule and all work should be completed by Friday 27 March. We would
like to thank the residents and business for their patience and understanding
whilst this work is taking place

Upcoming work

Estimated completion date

27 March 2020

COMPLETE - 10 MAR 2020

Complete - 100%

Start date

24 February 2020

Work completed

Union Lane
Work was completed bertween 24 February - 10 March.

Work in Progress

Upcoming work

Estimated completion date

10 March 2020

COMPLETE - 10 MAR 2020

Complete - 100%

Start date

24 February 2020

Work completed

Kidderminster Road
Work was completed bertween 24 February - 10 March.

Work in Progress

Upcoming work

Estimated completion date

10 March 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Sarah Miles

Amey Customer Service Officer

07716227712