Our progress so far
We plan to start the water main renewals from 4 January 2021, on a section of Forshaw Heath Lane. Work will be carried out in two phases, starting close to the M42 bridge near Birmingham and Solihull Rugby Club and moving towards The Limes Country Inn.
IN PROGRESS
Road closure
To allow us to complete this work quickly and safely we will have road closures in place. This is to ensure your safety and the safety of our workforce. There will be no through road access and there will be a signposted diversion route in place, you may wish to allow extra time for your journey.
Roads affected:
Forshaw Heath Lane
Progress - 0%
Start date
4 January 2021
Upcoming work
We plan to start the water main renewals on this phase from 4 January 2021.
Work in Progress
Work completed
Estimated completion date
15 January 2021
IN PROGRESS
Progress - 0%
Start date
11 January 2021
Upcoming work
Work in Progress
Work on phase two has now been brought forward and we started on 11 January 2021.
Work completed
Estimated completion date
12 March 2021
Taking care of one of life's essentials
Securing your supply
Three months in the works
New pipes for old
Let us know how we're doing
Please get in touch if you have any feedback about our works.
Meet the team
Samantha Pedley
Amey Customer Service Officer
07725 073188