In My Area

Planned improvements

Finham Sewage Treatment Works - Finham Sewerage Treatment Works

We're investing over £35 million to upgrade Finham Sewage Treatment Works to make sure it remains fit for purpose well into the future.

65%

In progress

30 Oct 2019

Estimated completion date
Upcoming work
Work in progress
Sludge pumps

The sludge pumps have been in operation for over a year and performing well. Over 50% of the works on the Activated Sludge Plant and CoMag technology is complete and progressing well.

Finham Sewage Treatment Works

Next month the newly installed sludge pump should be commissioned. The planning application for Phase 2 has now been approved. The works on the Activated Sludge Plant is underway and progressing well.

Work completed
27 July 2017 - Customer drop-in session

So that we can share our plans and answer any questions you might have we've arranged a customer drop-in session on 27 July 2017, at St. Martin's Church, 136 Green Lane, Coventry, CV3 6EA, 1:30pm - 7:00pm.

Start date

05 Jun 2017

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Richard Green - Costain

Project Manager

Manjit Chadha

Programme Manager

STWater Twitter

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages