Elan Valley Aqueduct - Severn Siphon

100%

Complete

31 May 2018

Estimated completion date
Upcoming work
Work in progress
Work completed
Severn Siphon

Start of site preparation - May 2017

Severn Siphon

Site reinstatement complete - May 2018

Start date

17 May 2017

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Updates

The Elan Valley Aqueduct (EVA) is over 100 years old and so is in need of some modernisation. We cannot shut down the EVA to carry out work, as it provides a vital water supply for Birmingham. We are therefore building new bypass sections alongside the EVA at Bleddfa, Nantmel and Knighton where the EVA needs refurbishment. To create each bypass a shaft is first built at either end and a 3 metre diameter tunnel boring machine is then driven underground to cut the new bypass tunnel between the shafts. Once the bypass is complete the new section is connected to the EVA. This means most of the work is not noticeable above ground and can be completed without interruption to the EVA flow.

To find out more about Birmingham's water supply click here.

Tunnel Boring Machine at Bleddfa

Why are we doing this?

Meet the team

Ken MacGregor

Project Director

Paul Dennison

Programme Manager

STwater

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages