Planned improvements

Elan Valley Aqueduct - Knighton

43%

In progress

30 Aug 2019

Estimated completion date
Upcoming work
Knighton

Site reinstatement complete - August 2019.

Knighton

End of underground tunnelling - November 2018 (at Presteigne Road).

Knighton

Work on pipework in school field - Summer 2018.

Work in progress
Knighton

Start downstream site set-up (Presteigne Road, B4355) - February 2018.

Knighton

Start of underground tunnelling - February 2018 (from Pennybont Road site).

Work completed

Knighton

Start of site preparation - April 2017.

Knighton

Start upstream site set-up (Pennybont Road, A488) - April 2017.

Start date

01 May 2017

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Updates

The Elan Valley Aqueduct (EVA) is over 100 years old and so is in need of some modernisation. We cannot shut down the EVA to carry out work, as it provides a vital water supply for Birmingham. We are therefore building new bypass sections alongside the EVA at Bleddfa, Nantmel and Knighton where the EVA needs refurbishment. To create each bypass a shaft is first built at either end and a 3 metre diameter tunnel boring machine is then driven underground to cut the new bypass tunnel between the shafts. Once the bypass is complete the new section is connected to the EVA. This means most of the work is not noticeable above ground and can be completed without interruption to the EVA flow.

For more information on the Birmingham Resilience Project click here.

Tunnel Boring Machine at Bleddfa

Why are we doing this?

Meet the team

Ken MacGregor

Project Director

Paul Dennison

Programme Manager

STwater

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages