In My Area

Planned improvements

East and Central Newark - East and Central Newark - Water Improvements

We're renewing some of the existing water pipes to reduce the risk of bursts and discoloration. We are also planning to install a number of new valves across our network to improve flexibility, however these valve works are small scale and are not included in the descriptions below.

80%

In progress

31 May 2019

Estimated completion date
Upcoming work
Water Mains Renewal

We are going to be doing Mains Renewal Works in and around Lincoln Road Bridge, this will help to reduce the risk of supply interruptions and discoloration. This work is planned to start on 7 May 2019. There will be traffic management required around the 13 May 2019 for a few days, which will consist of temporary lane closure on North Gate, near the junction with Queens Road

Sluice Valves (SVs)

We are going to install a new Sluice Valve at Beacon Heights. This will help us reduce the risk of supply interruptions. This work is scheduled to commence in May 2019 and will take between three and four weeks to complete.

Work in progress
New supply and distribution mains

Construction of 11km of new, clean water supply and distribution pipes, across fields to the East of the town, is progressing well. As part of the process, topsoil is stripped and pipes are then laid before being backfilled. We have installed over 10km of the pipes. The new pipes will help to ensure that Newark has a resilient water supply now and in the future, providing for the 42% population increase that is included as part of Newark and Sherwood District Council's local plan.

Work completed
Blatherwick Road - water main renewal

We have finished replacing the existing water mains on Blatherwick Road, this will help to reduce the risk of supply interruptions and discoloration.

Trent Crossing works

We installed the final part of our Trent Crossing Works on Tolney Lane in February, meaning this package of works is now completed. Along with the additional new water pipeline near to the Great North Road Trent Crossing and new short section of pipework on The Wharf, this will help us reduce the risk of supply interruptions due to bursts.

Great North Road

We have finished installing a new additional water pipeline near to the Great North Road River Trent Crossing. This will help us reduce the risk of supply interruptions due to pipe bursting.

Pressure reducing valves (PRVs)

A new PRV has been installed on Barnby Gate. This will help to reduce the risk of supply interruptions caused by burst pipes.

Sluice valves

A new Sluice Valve has now been installed at Sleaford Road. This will help to reduce the risk of supply interruptions.

Start date

01 Aug 2017

  • Roads effected:

There are currently no disruptions

There are currently no disruptions

When will this work affect you?

We'll be working in Newark over the next four years- watch our video for more information

Why are we doing this?

Meet the team

Nicholas Wallace

Senior Programme Engineer

Charlotte Crake

Customer Liaison Officer BNM

Rupert Tagg

Project Director

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages