Derwen, Oswestry

We’re committed to making sure our customers receive a continuous supply of water now and in the future. So, we’re constantly checking the condition of our network and recognise that we need to upgrade some of the water pipes in the Derwen area. 

Our progress so far

We plan to start the water main renewals in the area from 7 June 2021 and the work will be done in five phases. To safely carry out the water main renewals we will have road closures in place.

Our Progress

Start date

7 June 2021

Upcoming work

Work in Progress

Work completed

We are pleased to confirm we have completed Phase one – The Bryn junction to Gornal, we undertook  the work in the grass verge to minimise the disruption to the residents and businesses within the local area, we would like to thank them for their patience whilst this work took place. 

Estimated completion date

25 June 2021

Our Progress

Start date

28 June 2021

Upcoming work

Work in Progress

Work completed

We are pleased to confirm we have completed work on Phase 2.

Estimated completion date

5 September 2021

Road Closure

To allow us to carry out this work quickly and safely, our team will be working under a road closure.

Roads affected:

Iron Mills junction to B5009, Whittington Road

Our Progress

Start date

9 August 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

22 October 2021

map of the road works and diversion route in Derwen

Signs and Barriers

To allow us to carry out this work quickly and safely, our team will be working with signs and barirers in place to restrict the traffic flow.

Roads affected:

B5009, Whittington Road

Progress - 0%

Start date

25 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

26 November 2021

Road Closure

To allow us to carry out this work quickly and safely, our team will be working under a road closure.

Roads affected:

Twmpath Lane (between B5009, Whittington Road & Meadowbrok Court)

Progress - 0%

Start date

25 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

26 November 2021

Taking care of one of life's essentials


Let us know how we're doing

Please get in touch if you have any feedback about our works.


Meet the team

Sarah Miles

Amey Customer Service Officer

07716 227712