Crow Lane

We’re carrying out maintenance on Summerley Road and replacing some of the water pipes on Crow Lane to ensure supplies of wonderful water for the future. 

Our progress so far

The team will start work on Summerley Road close to the junction of Gipsy Lane week commencing 11 October 2021, they will then move onto Crow Lane from the junction of Staton Lane and complete on Crow Lane by the middle of February 2022. 

UPCOMING

Three-way traffic lights

Due to the location of the pipe and to allow us to carry out this work safely, we’ve agreed with the local authority to slow down the flow of traffic by using traffic lights around our working area and multiway traffic lights at junctions. 

Roads affected:

Summerley Road

Our Progress

Start date

11 October 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

1 November 2021

Two-way and four-way traffic lights

Due to the location of the pipe and to allow us to carry out this work safely, we’ve agreed with the local authority to slow down the flow of traffic by using traffic lights around our working area and multiway traffic lights at junctions. 

Roads affected:

Crow Lane and Staton Lane

Our Progress

Start date

1 November 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

13 December 2021

Two-way and three-way traffic lights

Due to the location of the pipe and to allow us to carry out this work safely, we’ve agreed with the local authority to slow down the flow of traffic by using traffic lights around our working area and multiway traffic lights at junctions. 

Roads affected:

Crow Lane and Hundall Lane

Our Progress

Start date

13 December 2021

Upcoming work

Work in Progress

Work completed

Estimated completion date

24 January 2022

UPCOMING

Three-way traffic lights

Due to the location of the pipe and to allow us to carry out this work safely, we’ve agreed with the local authority to slow down the flow of traffic by using traffic lights around our working area and multiway traffic lights at junctions. 

Roads affected:

Crow Lane

Our Progress

Start date

24 January 2022

Upcoming work

Work in Progress

Work completed

Estimated completion date

7 February 2022

Taking care of one of life's essentials


Let us know how we're doing

Please get in touch if you have any feedback about our works.


Meet the team

Lisa Orme

Severn Trent Community Communications Officer

07790 845234