We're carrying out water pipe inmprovements across Birmingham to secure water supplies for the future.

Our progress so far

Every so often, we need to replace old water pipes. That’s because the likelihood of any problems occurring increases as the years pass, so we’re replacing the old pipes in Frankley Green with some brand-new ones.

IN PROGRESS

Road closure

In order to keep you and our workforce safe, we’ll need to complete the work under a road- closure and use multi-way traffic lights whilst working in any junctions. There will be a signposted diversion in place using Ravenhayes Lane, Balmoral Road and Scotland Lane as a route around the closure.

Roads affected:

Church Hill

Progress - 0%

Start date

1 February 2021

Upcoming work

Work in Progress

The work will start week commencing 1 February 2021 and will take three months to complete. Our team will start at the junction of Frankley Lane and Scotland Lane and will progress along Church Hill and finishing at the Ravenhayes Lane junction.

Work completed

Estimated completion date

7 May 2021

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Timothy Ip

Severn Trent Community Communications Officer

07789 903918