Buxton and (surrounding area) water improvement project - Chelmorton Village

80%

Final phase

31 May 2019

Estimated completion date
Upcoming work

The team will be working on Main Street for the next three weeks to complete some serve connections. There will be signs and barriers around the holes whilst the work is carried out. The team will be on site until Mid- July.

Work in progress
Work completed
Main Street

Work will take place on main street week commencing 15 October. There will be traffic lights in place for the duration of the work. Once completed the team will move onto The Ditch.

The team are currently on Main Street, the foam concrete was put down on Tuesday and it takes 24 hours to dry. The reinstatement team will be on site Thursday 18 April. The team will be back on site Tuesday 23 April to complete the work.

Start date

15 Oct 2018

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Meet the team

Rachel Lowe

Community Communications Officer - Severn Trent

How are we doing?

If you have any feedback about our works, please click the button below.