In My Area

Planned improvements

Buxton and (surrounding area) water improvement project - Burlow Road

100%

Complete

28 Jun 2019

Estimated completion date
Upcoming work
Work in progress
Work completed

The team have been working on Heathfield Nook and will need to go back in May to complete the last section up to the railway bridge. The team also need to complete work on Barson Grove which should be starting the end of May.

The team have completed work on Burlow Road and under the railway bridge, they have also completed a section of work on Heathfield Nook Road but have had to stop due to Network Rail completing maintenance to the bridge.

Burlow Road

The team will start on site week commencing 29 October 2018, at the junction of Burlow Avenue and Burlow Road. Then will work their way down to the Caravan Park on Brierlow Road. Due to the width of the railway bridge, there will be a road closure on Burlow Road – 7 January 2019 for 4 weeks.

The team will be working on Brierlow Road for approximately 7 weeks, there will be traffic lights in place for the duration of the work.

Start date

29 Oct 2018

There are currently no disruptions

There are currently no disruptions

Parking

Parking

We may need some residents to park further down the road as our work progresses.

  • Locations effected:

Meet the team

Rachel Lowe

Community Communications Officer - Severn Trent

How are we doing?

If you have any feedback about our works, please click the button below.

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us