We’re constantly checking the condition of our network and recognise that we need to upgrade some of the water pipes in the Broad Lane area.

Our progress so far

Progress - 100%

Start date

18 May 2020

Upcoming work

Work in Progress

Work completed

The work on Phase one is now complete.

Estimated completion date

7 August 2020

Progress - 100%

Start date

8 June 2020

Upcoming work

Work in Progress

Work completed

The work on phase two is now complete.

Estimated completion date

7 August 2020

Road closure

To allow us to complete this work quickly and safely we will have a road closure in place between the junction of Vicarage Hill and B4102, a signposted diversion route will be in place.

Roads affected:

Broad Lane between Vicarage Hill and B4102

Progress - 0%

Start date

30 September 2020

Upcoming work

Work in Progress

Our team have made slow progress due to a number of engineering difficulties, however, we have moved beyond the entrance into Wood End Lane. From approximately 30 September 2020 access up to Wood End Lane should now be from the Poolhead Lane end of Broad lane and includes access to the Warwickshire Lad and doctor’s surgery. 

Residents on the other side of Wood End Lane should continue to access from The Common end of Broad lane. We will always keep access to properties or businesses within the closure, including access for emergency services, but access will be from one side or the other of the working area.

There will be no through road with a signposted diversion route in place, you may wish to allow extra time for your journey. 

Work completed

Estimated completion date

16 October 2020

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.

Meet the team

Samantha Pedley

Amey Customer Service Officer

07725 073188