Bishops Offley, Staffordshire - Phase two

60%

In progress

06 Jul 2018

Estimated completion date
Upcoming work
Work in progress
Phase two - Bishops Offley

This week works have been slightly slower than previous due to change of the ground conditions we have experienced, we have reverted to the use of a trenching method to installed the water mains near manor farm, works will continue and our team will work hard through the current conditions to install the new water pipes heading towards the village as quickly as possible. Access to frontage will be maintained where possible during this work, please allow added time on your journeys to avoid any delays.

Work completed
Start date

23 Apr 2018

Road closure

Road closure

We'll be closing parts of the road during our works, so that we can works quickly and safely.

  • Roads effected:
  • Doley Road and Rock View

There are currently no disruptions

Parking

Parking

Parking around the work will cause congestion and delays due to the plant and machinery required for us to carry out these works. We’re really sorry about this, but it will mean we keep everyone safe and get the work done as quickly as possible.

  • Locations effected:

Why are we doing this?

Meet the team

Steve Coventry

Amey Customer Liaison Officer

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages