In My Area

Birmingham Resilience Project

Work started in 2016 to lay a new 26km pipeline from the River Severn near Stourport to our water treatment works at Frankley. The new pipeline will significantly improve resilience of the water supply for over 1.2 million customers across Birmingham and surrounding areas.

Our progress so far

IN PROGRESS - 30 JUN 2020

In Progress - 90%

Start Date

1 March 2017

Work completed

  • Phase One - March 2017 to April 2017
    We've carried out preparation and ground work for the river intake and pumping station. Activities included putting up fencing, making an access road and the stripping away some of the topsoil. We will also set up the site offices and compound. We have also successfully tunnelled down to the location of the pumping station and will be in a position to thread the pipes through over the coming months.

  • Phase Two - April 2017 to December 2018
    We have created our site and an access road, including temporary carparks and working areas. We have also stripped back much of the topsoil and already started to lay the pipe. We have started to build the foundations for the new pumping station and the final part of tunnelling has commenced. During this phase we will build the main structures for the river intake and pumping station. This work starts with digging foundations and making provision for drainage. Some parts of the facility will be brought to site in component parts and put together on site. We have created a dam near the banks of the river. We can now begin to build the intake structure in the river. This will involve driving metal sheets in to the river bed. The footpath near our structure has been diverted. During July and August the final stage of tunnelling will commence as we bore down towards the river, building a new shaft to receive the tunnel boring machine. Some night time working will take place in this period.

Work in Progress

  • Phase Three - December 2018 to Spring 2019
    Electrical and mechanical work is still ongoing at Lickhill. The majority of the fitting, pumps and pipework has now been installation. Due to some unforeseen circumstances work on the inlet is running slightly behind schedule

Upcoming work

  • Phase Four - Due to complete early 2020
    With the facility now complete we will carry out testing. Teams will also be on site reinstating and landscaping the area.

Estimated completion date

30 June 2020

IN PROGRESS - 30 JUN 2020

In Progress - 85%

Start date

1 March 2017

Work completed

  • Phase One - March 2017 to April 2017
    We have carried out preparations and ground work for the Break Pressure Tank. Activities included putting up fencing and stripping away some topsoil. We also carried out excavation work to create a flat working area and setting up the site offices and compound. Signage will be in place to advise road users of the site entrance. We have removed all of the soil from the area which is known as muckshifting.

  • Phase Two - April 2017 to November 2018
    We have constructed much of the outer structure of the Break Pressure Tank, with just the office left to build. We have started to landscape around the structure itself. We will now concentrate on the internal structure and the drainage around the building. Some parts of the facility will be brought to Romsley in component parts and put together on site. We'll also continue to lay new water mains in the surrounding fields.

  • Phase Three - Spring 2018 to Winter 2018
    Once the main structures are complete we will commence electrical and mechanical work. This includes fitting the pumps and pipework, installation of systems to power the facility, and also the instrumentation and controls which will monitor the works once it is operational.

  • Phase Four - Completion expected end of 2018
    With the Break Pressure Tank now complete we will carry out extensive testing. Teams will be on site carrying out reinstatement and landscaping work to screen the site from public view, this will involve a tree planting scheme.

Work in Progress

  • Phase Five - Final reinstatement works
    Now that the hoppers have been installed we'll carry out the final reinstatement works on site. This has slowed due to the extensive pipeline testing which is still underway.

Upcoming work

Estimated completion date

30 June 2020

What we're doing

Work started in 2016 to lay a new 26km pipeline from the River Severn near Stourport on Severn to our water treatment works at Frankley. The pipeline begins at Lickhill where we are building a new pumping station and there is also a break pressure tank near Romsley. The new pipeline will significantly improve resilience of the water supply for over 1.2 million customers across Birmingham and surrounding areas. It will also support our wider network of pipes and so benefit customers right across the Severn Trent Region.

 

Taking care of one of life's essentials

Let us know how we're doing

Please get in touch if you have any feedback about our works.