Belpher Bridgefoot - Belper Bridgefoot

75%

In progress

29 Jun 2018

Estimated completion date
Upcoming work
Work in progress
Ashbourne Road

Further progress has been made. Cover slabs have now been installed on the wet well together with all electrical and mechanical equipment. We are now progressing with the commissioning, and finishing works. Hoping to be demobilising in the next couple of months.

Work completed
Construction access off Ashbourne Road

Works are still progressing well now that the shaft has been completed we'll begin to make the connections and install the mechanical and electrical equipment.

Start date

07 Aug 2017

Traffic management

Traffic management

For the first two weeks of our works we'll be using traffic management on Ashbourne Road. Please expect short delays.

  • Roads effected:
  • Ashbourne Road

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Meet the team

Tony Duerden

Site Agent

Graham Robinson

Senior Programme Engineer

STWater Twitter

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages