Ambergrove Sewage Pumping Station and Hagwood - Sewage Pumping Station upgrade

75%

In progress

28 Jun 2019

Estimated completion date
Upcoming work
Work in progress
Sewage Pumping Station upgrade

The construction of the new Ambergrove SPS chamber is complete as well as the mechanical and electrical installation. Remaining works at Ambergrove include the BT line connection for the site and reinstatement of the garden and verge. Hagwood SPS storage tank has now been constructed and the cover slab installed, next steps include the installation of the pumps, screen, handrails and reinstatement of the site.

Work completed
Start date

02 Jan 2019

There are currently no disruptions

There are currently no disruptions

There are currently no disruptions

Why are we doing this?

Tony Duerden

NMCN Site Manager

Rob Ward

nmcn Project Manager

Chris Carter

Severn Trent Engineer

How are we doing?

If you have any feedback about our works, please click the button below.

Phone (expands content) (collapses content)

Emergencies (24hrs)

0800 783 4444

Billing Enquiries

0345 750 0500

Email (expands content) (collapses content)

Feel free to email us with any enquiries

Contact us
Languages (expands content) (collapses content)

Get help in your preferred language

Other languages